• Post Reply Bookmark Topic Watch Topic
  • New Topic
permaculture forums growies critters building homesteading energy monies kitchen purity ungarbage community wilderness fiber arts art permaculture artisans regional education skip experiences global resources cider press projects digital market permies.com pie forums private forums all forums
this forum made possible by our volunteer staff, including ...
master stewards:
  • Nancy Reading
  • Carla Burke
  • r ranson
  • John F Dean
  • paul wheaton
  • Pearl Sutton
stewards:
  • Jay Angler
  • Liv Smith
  • Leigh Tate
master gardeners:
  • Christopher Weeks
  • Timothy Norton
gardeners:
  • thomas rubino
  • Jeremy VanGelder
  • Maieshe Ljin

BIMA Digester Working Principle?

 
Posts: 5
  • Likes 1
  • Mark post as helpful
  • send pies
    Number of slices to send:
    Optional 'thank-you' note:
  • Quote
  • Report post to moderator
Hello Friends,

At the moment I am working in CSTR digestion process, I will be started working in BIMA (Biogas Induced Mixing Arrangement) in the coming days. Can anyone explain me the working principle of BIMA digester process and share any references if you have, will be very helpful for me.

Thanks.
 
Posts: 1
  • Mark post as helpful
  • send pies
    Number of slices to send:
    Optional 'thank-you' note:
  • Quote
  • Report post to moderator
Hi Gerald,
Operating Principle of BIMA digester.

BIMA digester is divided into 3 separate sections, being connected liquid and gas wise. The three sections are the main chamber, the upper chamber and the central tube, to which the feed-pipe is connected. In this central tube prehydrolysis of the substrate takes place. Most of the biogas is generated in the main chamber through the decomposition of organic materials. By closing an automatic valve in the gas pipe between the two chambers the gas produced in the main chamber is collected there, which in turn displaces an equal amount of the digested substrate into the upper chamber, building a level of difference and thus a gas pressure in the main chamber. When the required level difference is achieved (mixing pressure), the gas pressure is released by opening the automatic valve in the gas connecting pipe. Thus the substrate displaced into the upper chamber flows back to the main chamber with high velocity. A portion of the waste flows to the main chamber through the mixing wings while the rest flows back through the mixing shafts. On account of this, fresh substrate, scum and sediments are perfectly remixed with the contents of the main chamber. Thus the new pre-hydrolyzed substrate is mixed with active biomass in the digester. Another portion of the digested substrate, which flows out through the mixing shafts, pours onto the surface of the main chamber, thus avoiding formation of scum.

Regards
Srinivas Kasulla
srinivaskasulla@gmail.com
srinivaskasulla@xeonwm.com
 
gerald lappus
Posts: 5
  • Mark post as helpful
  • send pies
    Number of slices to send:
    Optional 'thank-you' note:
  • Quote
  • Report post to moderator
Thanks for the explanation, it is very useful for me.

Srinivas Kasulla wrote:Hi Gerald,
Operating Principle of BIMA digester.

BIMA digester is divided into 3 separate sections, being connected liquid and gas wise. The three sections are the main chamber, the upper chamber and the central tube, to which the feed-pipe is connected. In this central tube prehydrolysis of the substrate takes place. Most of the biogas is generated in the main chamber through the decomposition of organic materials. By closing an automatic valve in the gas pipe between the two chambers the gas produced in the main chamber is collected there, which in turn displaces an equal amount of the digested substrate into the upper chamber, building a level of difference and thus a gas pressure in the main chamber. When the required level difference is achieved (mixing pressure), the gas pressure is released by opening the automatic valve in the gas connecting pipe. Thus the substrate displaced into the upper chamber flows back to the main chamber with high velocity. A portion of the waste flows to the main chamber through the mixing wings while the rest flows back through the mixing shafts. On account of this, fresh substrate, scum and sediments are perfectly remixed with the contents of the main chamber. Thus the new pre-hydrolyzed substrate is mixed with active biomass in the digester. Another portion of the digested substrate, which flows out through the mixing shafts, pours onto the surface of the main chamber, thus avoiding formation of scum.

Regards
Srinivas Kasulla
srinivaskasulla@gmail.com
srinivaskasulla@xeonwm.com

 
Destroy anything that stands in your way. Except this tiny ad:
permaculture and gardener gifts (stocking stuffers?)
https://permies.com/wiki/permaculture-gifts-stocking-stuffers
reply
    Bookmark Topic Watch Topic
  • New Topic