Cedric Noussan

pollinator
+ Follow
since Dec 09, 2022
Merit badge: bb list bbv list
For More
North italy
Apples and Likes
Apples
Total received
In last 30 days
0
Forums and Threads

Recent posts by Cedric Noussan

Cristobal Cristo wrote:
Is it an open space or just one floor of the house with interior walls?



mainly an open space, just a few walls here and there, the rmh is in the center of the space
1 month ago

thomas rubino wrote:Excellent Job, Cedric!
In one photo, you show a plate blocking off the riser port?
Why? What was its purpose?  



if you mean photo 178, it's just the bypass, the perspective is deceiving
1 month ago
Work resumed a month later, when everything was completely dry.
An additional coat of lime plaster, a covering of the chimney flue outside the bell, and some metal decorations completed the job.
After a few months of use, I can only be satisfied. The house stays warm all day using half the wood! Incredible! You can't understand until you experience it for yourself.
What are you waiting for? Upgrade to an RMH!
1 month ago
Finally, the bell was closed with T-bars, superwhool, and firebrick, followed by a layer of superwhool and one of clinker (an excellent way to use up offcuts).
Plastering and first lighting: what a marvel!
https://youtube.com/shorts/3t2ybOkbe3E
1 month ago
Once we reached the right height, I positioned the core support and assembled and insulated it with superwhool.
The masonry work continued with a single skin up to the height of the combustion chamber. Subsequently, the inner layer will be firebrick while the outer layer will be clinker, the two layers separated by superwhool.
A bypass was installed above the riser
1 month ago
And here we are at the first part of work, seven days of hard work...
The first day was dedicated to wrapping the house and furniture in tarps to protect them from dust and demolishing the fireplace.
The work continued by tracing the perimeter of the bell and moving up the layers, cement clinker bonded with sand, lime, and Portland cement mortar.

1 month ago
After that, I have the procedure for cutting the bricks for the combustion unit
here the first burn: https://youtube.com/shorts/Ow7tqGgOBzw
1 month ago
The first part is dedicated to preparing the metal parts, cutting and welding of metal:  T-bar,inspection, by pass, door  and combustion unit support


1 month ago
After finding the final project I started to find the materials
for the refractory bricks and mortars, here unistara
For the iron, , here easy iron
I found the cement clinker, sand, and putty lime and the rest near my house.



1 month ago
The design began by looking for solutions to the constraints I had identified. Here are some questions I found answered on permies:
webpage

The combustion unit is 190 cm shorty, the size of the system is tied to the existing chimney (rectangular 15x30 cm), It was not possible to replace it or move it from its position without heavy demolition work.

Project continues with the design 3D on sketchup. The advice we received was fundamental, both regarding the materials and the arrangement of the various elements.
1 month ago