John Weiland wrote:Eric, I may have missed it in your build description, but do you have plastic/ABS separation sheets between each adjacent cell? I just received 4 EVE 100 Ah cells that will fit nicely in an ammo-box build but need to confirm the need or not for dividers as has been mentioned elsewhere on internet descriptions. Thanks!
Mike Haasl wrote:This is a badge bit (BB) that is part of the PEP curriculum. Completing this BB is part of getting the sand badge in Electricity.
In this Badge Bit, you will replace or install a permanent AC light fixture.
Wiring varies greatly, just be safe when pursuing this BB
To complete this BB, the minimum requirements are:
- install new or replace existing permanent AC light fixture
To show you've completed this Badge Bit, you must provide:
- a picture of the current location that needs a new light fixture
- a picture of the installation midway through
- a picture of the finished installation with the light turned on
Burra Maluca wrote:
Allen Jackson wrote: One 220VAC 30 amp RV outlet - There is NO such thing!
Well there is in Europe, but it's not the sort of thing I'd expect to find in an RV in the USA.
This BB is a PEP one so as far as I know it should be suitable for use in Montana, so I strongly suspect it's a typo and should read "One120VAC 30 amp RV outlet", not 220
Mike Barkley wrote:Allen you should be able to get most of it from here ... https://www.mcmaster.com/products/electrical-lighting/
John Weiland wrote:Thanks for these continued additions, Allen, and giving a personal shout-out to others who have helped a newbie like myself get knee-deep into solar/battery power so quickly. So much great experience and expertise here to help along interested members of the community.
I hope to add more soon regarding a larger desired system....likely 48V for reasons you and others have noted....and hope to take advantage of the current (and hopefully not disappearing???) deals on hybrid inverter systems for our home. This may be sized to handle full home loads, but as noted elsewhere may also just be targeted, at least initially, for critical loads like furnace, water-well, and sump-pumps. One item I did wish to bring up for discussion is your comment about 30A 220/240VAC outlet and perhaps I misunderstood your explanation. Below is the plug configuration for connecting our gas generator to the transfer switch on our utility (grid) power pole. It's rated for 30 amps and does indeed all for 120V and 220/240VAC through that same plug. In fact, I'm actually hoping to set up a hybrid inverter (pure sine wave, 12 - 15 kW) that would be connected to parallel-tied, 100 Ah batteries (scalable). The hope initially is just to charge the batteries from the grid to test out the interface, then add solar panels step-wise to fine the balance between cost and battery charging that appears to match our battery draw-down.
Now time for some crude math (sets up abacus...) I have gas gennies in the 7-9kW range, but only if I use 240V in the equation of 240 X 30 amps do I get the 7200W that the gennie is rated at. A question arises as to what might happen if I wire the inverter as split phase to provide both 120V and 240V across that same cable and into that same transfer switch: I'm assuming a (combined?) load larger than 30 A might be attempted, but at what point does this become dangerous? Pretty sure the generators are breaker protected so that if such a draw/load occurs, the breaker will be tripped, but I've not had this happen to date. I guess the question is whether the inverter 'AC OUT' terminals will have a breaker that one can size appropriately for all downstream considerations....wire size, etc.
Finally, the specs on the EVE 3.2V cells that you posted look very similar to the ones I'm looking at....only difference being the dimensions. The cells I'm looking at are ~1.4 inches thick, which will allow me to place them, along with appropriate dividers and bonding wrap, side-by-side into a ~6+ inch space. Additional space in the casing will easily allow for BMS and associated wiring. Fingers crossed!
, but I had to do that before the powerwall installation because they were blowing breakers and taking down the entire server room in the process when they were highly imbalanced -- then they chose to add more servers, and I had to upgrade the power feed, add the 2nd inverter, etc.