• Post Reply Bookmark Topic Watch Topic
  • New Topic
permaculture forums growies critters building homesteading energy monies kitchen purity ungarbage community wilderness fiber arts art permaculture artisans regional education skip experiences global resources cider press projects digital market permies.com pie forums private forums all forums
this forum made possible by our volunteer staff, including ...
master stewards:
  • Carla Burke
  • John F Dean
  • Timothy Norton
  • Nancy Reading
  • r ranson
  • Jay Angler
  • Pearl Sutton
stewards:
  • paul wheaton
  • Tereza Okava
  • AndrĂ©s Bernal
master gardeners:
  • Christopher Weeks
gardeners:
  • Jeremy VanGelder
  • M Ljin
  • Matt McSpadden

Distance from floor channel vertical secondary air tube and port entrance

 
pollinator
Posts: 132
9
  • Likes 1
  • Mark post as helpful
  • send pies
    Number of slices to send:
    Optional 'thank-you' note:
  • Quote
  • Report post to moderator
Working on my BB RMH and wondered what the recommended distance is from the floor channel vertical secondary air tube and the heat riser port entrance?

Many thanks for any help.
 
master rocket scientist
Posts: 6748
Location: latitude 47 N.W. montana zone 6A
3625
cat pig rocket stoves
  • Likes 2
  • Mark post as helpful
  • send pies
    Number of slices to send:
    Optional 'thank-you' note:
  • Quote
  • Report post to moderator
Hi John;
My secondary tubes have the 6" stub set back apx 1"
The tube itself is even with the back wall.
So I would say 3/4" -  1.5"  would be acceptable.


20210107_141247-1.jpg
[Thumbnail for 20210107_141247-1.jpg]
 
John Harrison
pollinator
Posts: 132
9
  • Likes 1
  • Mark post as helpful
  • send pies
    Number of slices to send:
    Optional 'thank-you' note:
  • Quote
  • Report post to moderator
Thanks very much Thomas - I'll give that a go!
gift
 
Unofficial Companion Guide to the Rocket Oven DVD
will be released to subscribers in: soon!
reply
    Bookmark Topic Watch Topic
  • New Topic